8/30/2021–no work performed today.
Construction Progress–8/27/2021
2 workers were on site. George mentioned that 9/6/2021 (or after this holiday) might start the seismic retrofitting. He will contact Luke Yu for the scheduling. Photos taken clockwise from the mid point of the north wall. (6:51 pm, 8/27/2021).
Construction Progress–8/26/2021
1 demolition worker is here for the entire day. Another worker came in late afternoon to put away the electrical flexible conduits.
Construction Progress–8/25/2021
Construction Progress–8/24/2021
Construction Progress–8/23/2021
There is minor work done today, primarily in taking down some of the light panels and coil up some electrical wire tubing. These are the light panels taken down from the ceiling. Albert Lin and I are in communication with DRA regarding the demolition plan. The plan calls for the removal of the short wall,…
Construction Progress-8/20/2021
David Ho (the owner of Ho’s Remodeling) was here and he with his workers set up aisleway at the side entrance for foot traffic safety. I had meeting with George Ho. Among other things, we discussed the following things concerning the door schedule: While DRA drawings call for new doors in door #112, #118. These…
Construction Progress – 8/19/2021
Three workers work today in the 1st floor demolition.
Construction Progress – 8/18/2021
3 Workers work on the demolition today. (Taken from the southern entrance door of phase 1. Photo goes clockwise. Photos taken at 1:00 pm, 8/18/2021) (Photos taken clockwise from the southern entrance door of phase 1. Photos taken at 3:00 pm, 8/18/2021)